RECENTLY, National Broadband Network (NBN) crews have completed necessary upgrades to the Fixed Wireless network in the Paps.

These works were a two stage upgrade, with the first stage taking place between February 17 and 25, with the second round of works starting on February 27 and continuing through to March 4.

NBN told the Mansfield Courier that additional time has been planned on March 5 and 6 as a contingency, and will only be used if required.